Leads4pass > Scrum > Scrum Certifications > SMC > SMC Online Practice Questions and Answers

SMC Online Practice Questions and Answers

Questions 4

Which of the following is a tool that can be used for communicating information related to risks?

A. Risk Burnup chart.

B. Risk Burndown chart.

C. Risk Progress chart.

D. Risk Tracking chart.

Buy Now
Questions 5

The Chief Scrum Master is a part of the Scrum Core Team that assembles to retrospect the project and to identify, document, and internalize the lessons learned. There are various tools to Retrospect Project during the Retrospect Project Meeting. Which of the following tools can be used in this process?

A. Gap analysis.

B. SWOT analysis.

C. Proof of Concept.

D. Speed Boat.

Buy Now
Questions 6

All of the following events and activities are examples of adaptation, EXCEPT:

A. Seeking help from team members

B. Experienced team members mentoring new members

C. Recording Lessons learned to improve processes and address problems

D. Using information radiators to track the project progress

Buy Now
Questions 7

Which of the following methods helps estimate the value provided by projects?

A. Internal Rate of Return

B. Net Rate of Return

C. Present Rate of Return

D. Estimated Rate of Return

Buy Now
Questions 8

A Scrum Team wants to conduct a meeting in which they plan to deliberate on ways to improve team collaboration and effectiveness in future. This can be identified as which type of meeting?

A. Sprint Planning meeting.

B. Review Sprint meeting.

C. Retrospect Project meeting.

D. Review Project meeting.

Buy Now
Questions 9

You are working in a $50 million project to remove weeds from National monument areas.

You are responsible for achieving maximum business value for the project, and represent the Voice of the

Customer. What role do you play in this project?

A. Scrum Master.

B. Product Owner.

C. Sponsor.

D. Scrum Guidance Board.

Buy Now
Questions 10

The Chief Scrum Master facilitates the Scrum of Scrums Meeting. Which of the following statements about a Scrum of Scrums Meeting is true?

A. This meeting can be conducted at any time without any pre-determined intervals.

B. This meeting can be scaled up.

C. This meeting is always time-boxed.

D. This meeting is relevant only for high-investment projects.

Buy Now
Questions 11

Which of the following is NOT a Scrum Master's responsibility?

A. Groom the Prioritized Product Backlog.

B. Coordinate creation of Release Planning Schedule.

C. Facilitate Prioritized Product Backlog Review Meetings.

D. Represent the Scrum Core Team to provide lessons from the project.

Buy Now
Questions 12

What is Quality Assurance?

A. The evaluation of processes and standards that govern quality management in a project to ensure that they continue to be relevant.

B. Identification and definition of the product required from a Sprint and the project along with the Acceptance Criteria, any development methods to be followed, and the key responsibilities of Scrum Team members in regards to quality.

C. The execution of the planned quality activities by the Scrum Team in the process of creating deliverables that are potentially shippable.

D. A Scrum approach in which the team learns from experience and stakeholder engagement to constantly keep the Prioritized Product Backlog updated with any changes in requirements.

Buy Now
Questions 13

Which of the following is NOT an objective of a Retrospect Sprint Meeting?

A. Identify Process Improvements.

B. Identify Feature Improvements.

C. Identify Best Practices.

D. Identify Process problems and bottlenecks.

Buy Now