Which TWO are the purposes of a highlight report?
1.
To describe the MoSCoW priority of user stories.
2.
To summarize the status of a work package.
3.
To summarize the stage status.
4.
To report any potential issues and risks
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Which two statements about tailoring the business case in an agile environment are CORRECT?
1.
It should be unnecessary because products of the highest value will be delivered first.
2.
It should identify the minimum viable product and when it will be delivered.
3.
It should take into account that the scope may be reduced during the course of the project.
4.
It should show the features, the order in which they will be delivered and any dependencies.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
Which is a purpose of the `controlling stage' process?
A. To execute and deliver the project product
B. To establish whether the project is complete
C. To report stage progress to the project board
D. To draft the plan for the next stage's work
Which statement describes the Kanban approach?
A. It is used to make system improvements using visualization and by controlling work in progress
B. It is an iterative timeboxed approach that helps teams generate value
C. It was originally focused in creating new companies and is now used to speed up product delivery
D. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
What information is NOT typically displayed on a burn chart?
A. Effort remaining
B. Definition of `ready'
C. Actual amount of work done
D. Amount of time elapsed
In Scrum, what answers the question `what can be done this sprint?'
A. Daily scrum
B. Sprint review
C. Sprint planning
D. Increment
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
A. Using visualization to display information
B. Using meeting minutes to share decisions
C. Using social media to reach more people
D. Using email to document discussions
How is the `tailor to suit the project' principle applied in an agile context?
A. By flexing what is produced to stay in control and deliver value
B. By emphasizing tolerances on what is being delivered
C. By using the Agilometer to assess the project environment
D. By fitting releases into planned management stages
Which statement explains how the `learn from experience' principle is applied in an agile context?
A. It focuses on the prioritization and decomposition of requirements
B. It integrates releases within management stages
C. It is supported by the `inspect and adapt' concept
D. It provides guidance on mapping PRINCE2 roles to an agile environment
Which is a purpose of the quality theme?
A. To define the specific conditions that enable a product to be usable
B. To determine how the means of delivering products is communicated
C. To evaluate whether the project continues to be achievable
D. To assess any potential improvements to a product