SIMULATION
During the project execution phase, Ann, a project manager, received an email from the project sponsor asking for an additional work package to be added to the project scope due to new legislation.
INSTRUCTIONS
Review the email with the latest updates sent by the project sponsor and respond in the following order:
1.
Select the best tool for tracking the server migration progress.
2.
Select the new critical path.
3.
Select the correct number of engineers required for the server migration phase.
If at any time you would like to bring back the initial state of the simulation, please click the Reset All button.

Select the Appropriate Tool:


Select the new critical path. Option A

Option B

Option C

A. Check the answer in explanation.
B. PlaceHolder
C. PlaceHolder
D. PlaceHolder
Which of the following activities would a project manager perform during the closing phase? (Select THREE).
A. Lessons learned
B. Risk analysis
C. Removing resources
D. Acquiring resources
E. Statement of work sign-off
F. Stakeholder analysis
G. Removing access

Given the following network diagram:
Which of the following is the critical path?
A. A-C-G-K-M
B. A-B-D-l-L-M
C. A-B-E-J-L-M
D. A-B-F-L-M
A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?
A. Key stakeholder identification
B. Preliminary procurement
C. Solution design determination
D. Critical factor enlistment
A project manager provided details regarding the completion of the following tasks:
Vendor selection took less time than planned.
Equipment procurement took less time than estimated.
Equipment installation went according to schedule.
Which of the following should the project manager update?
A. Change log
B. Project Gantt
C. Issue log
D. Requirements traceability matrix
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
A. Add a new risk.
B. Perform an impact analysis.
C. Escalate to the sponsor.
D. Raise a change request.
A PM is responsible for implementing a new customer relationship management system and has learned that the sales organization is reluctant to utilize the new system. The organization's reluctance could jeopardize the success of the project. Which of the following steps should be taken to understand the adoption issues and gain organizational acceptance of the initiative? (Select TWO).
A. Train users on the proper use of the system.
B. Escalate the issue to the CCB
C. Hold sessions to understand user challenges.
D. Track system usage and report user activity.
E. Log the issue in the project risk register.
F. Create a memorandum of acceptable use.
A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?
A. Make an impact assessment.
B. Prepare a new purchase order.
C. Select a new vendor.
D. Create a risk register.
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
A. Procurement
B. Communication
C. Quality assurance
D. Risk
A project was closed according to the planned project schedule. Security teams later identified that one of the contractors stole data after the project's closure. Which of the following would have most likely prevented the data from being stolen?
A. Removing access
B. Closing contracts
C. Project sign-off
D. Project evaluation