You are using DMO of SUM. You defined 40 parallel R3load processes during uptime and 80 parallel R3load processes during downtime.
The server provides 8 CPU cores. Phase EU_CLONE_MIG_DT_RUN is running. In the Charts Control Center you can see 40 Process Buckets being executed in parallel.
Why are 40 Process Buckets executed in parallel?
Please choose the correct answer.
Response:
A. There is a maximum of 40 parallel R31oad processes within this specific downtime phase.
B. SUM is still running in uptime; the number of 40 defined R31oad processes is considered.
C. The number of CPU cores does not allow more than 40 R31oad processes to be run in parallel.
D. These are 40 pairs of R3load processes, so there are 80 R3load processes running.
Which of the following SUM activities require a stack XML file calculated by the maintenance planner? Note: There are 3 correct answers to this question.
A. SAP S/4HANA conversion including DMO
B. Prerequisite check
C. DMO without system update
D. SAP S/4HANA conversion without DMO
E. Benchmark tool
Which additional configuration options are offered by SUM when selecting "Switch expert mode on" in main configuration option "Standard"?
There are 2 correct answers to this question.
Response:
A. Keep archiving on during the whole procedure.
B. Use the Near Zero Downtime Maintenance Technology (NZDM).
C. Reuse a profile for the shadow instance from a previous run.
D. Choose the instance number of the shadow instance.
In which part of an upgrade does SUM allow you to generate ABAP loads (SGEN)? There are 2 correct answers to this question.
A. During downtime
B. During SPDD
C. Post-downtime
D. During uptime
Which step can be optimized when you provide the MIGRATE_DT_DUR.XML file to SUM?
A. Shadow on target creation
B. Downtime conversion
C. Silent data migration (SDM)
D. Downtime migration
You are planning an SAP S/4HANA conversion. Which conversion-specific tasks need to be performed during the preparation phase?
There are 2 correct answers to this question.
Response:
A. Run the database migration to the SAP HANA database
B. Perform the migration of data into the new data structure
C. Check the compatibility of custom code with SAP S/4HANA
D. Apply the recommendations of the simplification list
What is the main purpose of performing benchmark runs for an SAP S/4HANA conversion?
A. To optimize the migration
B. To optimize the activation
C. To optimize the conversion
D. To optimize the main import
What SAP systems can you use for the ABAP Test Cockpit (ATC) to perform the custom code analysis for an SAP S/4HANA conversion? Note: There are 2 correct answers to this question.
A. Standalone AS ABAP with SAP_BASIS 752 and above
B. SAP ECC system from SAP ERP 6.0 EHP 8
C. SAP Solution Manager 7.2
D. SAP S/4HANA Server 1809 and above
Regarding an SAP Upgrade, What does the major SAP Note for the version of SUM you are using usually contain?
A. The link to different patch levels to SUM
B. AA
C. The corrections to the SUM Guide
D. An overview about possible upgrade paths
You want to use the downtime-optimized data conversion for your SAP S/4HANA conversion. What is the main difference from a standard SAP S/4HANA conversion?
Please choose the correct answer.
Response:
A. An additional temporary database is used during uptime
B. Dedicated application tables are migrated in uptime
C. TABIMJJPG is executed in uptime
D. The repository is migrated in uptime