Leads4pass > Test Prep > Test Prep Certifications > CCE-CCC > CCE-CCC Online Practice Questions and Answers

CCE-CCC Online Practice Questions and Answers

Questions 4

Which of the following is NOT an aspect of quality management?

A. Quality assurance

B. Quality planning

C. Quality checking

D. Quality control

Buy Now
Questions 5

____________ is defined as covering work whose component activities are less defined and whose interrelationships are conditional.

A. Soft logic

B. Hard logic

C. Deductive logic

D. Inductive logic

Buy Now
Questions 6

______________can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.

A. Economic optimization

B. Simulation

C. Linear programming

D. Dynamic programming

Buy Now
Questions 7

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?

A. 16,215

B. 14,201

C. 12,000

D. 10,526

Buy Now
Questions 8

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs amounting to $55.00/unit?

A. 22.22%

B. $55.00

C. 2

D. 338.5

Buy Now
Questions 9

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the method to estimate the cost of the new rides:

A. Break down the technology into components

B. Call vendors for quotes

C. Use historical data from past projects

D. Adjust known data from existing rides

Buy Now
Questions 10

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:

A. To be exactly the percentages stated

B. To fall within the percentage range stated

C. To be higher or lower that the percentages stated

D. To be outside the percentages stated

Buy Now
Questions 11

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

After an individual's safety needs are met, what needs would the individual be motivated to fulfill next in Maslow's hierarchy of needs?

A. Belonging needs

B. Self-actualization

C. Knowledge

D. Pay and compensation

Buy Now
Questions 12

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Annual estimated tax would be:

A. $3,869

B. $5,565

C. $10,500

D. $11,925

Buy Now
Questions 13

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If you buy a lot for $3,000 and sell it for $6,000 at the end of 8 years, what is your annual rate of return?

A. 10.4%

B. 9.1%

C. 8.3%

D. 9.9%

Buy Now
Exam Code: CCE-CCC
Exam Name: Certified Cost Consultant / Cost Engineer (AACE International)
Last Update: Jul 06, 2026
Questions: 115
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99