Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct answers to this question
A. The materials must allow sales order or project stock
B. The exact lot size procedure must be used
C. The procurement type of the material must be internal
D. An MRP group must be assigned
How are earliest dates and latest dates of activities scheduled?
A. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates
B. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling
C. Earliest dates and latest dates are scheduled by forward scheduling
D. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling
How can you record external service activities with service master data? Note: There are 2 correct answers to this question
A. Confirm the network activity for external service
B. Confirm the activities in the Cross-Application Time Sheet (CATS)
C. Post a goods receipt in the goods movement application (MIGO)
D. Create a service entry sheet
Which of the following statements are true? Choose the correct answers. There are 2 correct answers to this question.
A. You can map a project using only one WBS or one network.
B. You can also represent a project using a WBS and one or more networks.
C. You can create a project based on a Activity.
D. You cannot use the characteristics of both the structures (WBS and Networks) together to represent a project.
Resources
Which of the following transactions can you use to post actual cost for external processing?
Note : there are 2 correct answer for this question.
A. Approval of a service entry sheet
B. Posting a goods receipt
C. Creating a service entry sheet
D. Approval of a good receipt.
E. Creating a purchase order.
A customer project must be finished at a given due date. The project consists of WBS elements and networks. What scheduling type do you use?
A. Only capacity requirements
B. Forward
C. Current date
D. Backward
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
A. Project versions can be changed
B. Project versions are mandatory for Milestone Trend Analysis (MTA)
C. Project versions can be created automatically based on user status
D. Manually Created project versions always require a project version profile
A service company uses project management and they complain that the system does not prevent their project managers from exceeding their budgets. What actions do you have to take to solve the problem?
A. Activate availability control for the WBS elements. Define the tolerance limits on each WBS element
B. Activate availability control in the assigned budget profile. Define the tolerance limits in customizing
C. Activate commitment management in the project definition Enter the budget in the master data of the top WBS element
D. Activate availability control for projects in the controlling area. Enter the plan data for each WBS element
Budgeting is implemented for projects. The budget has been adjusted several times. What standard report type provides an overview of adjustments on the budget?
A. Structure overview for budgets
B. Hierarchical report on budget updates
C. Cost element report on budget updates
D. Line item report for budgets
Which statement is valid regarding networks?
A. A network activity can be assigned to several WBS elements
B. Material components can be assigned to activity elements
C. Relationships can be used to connect activities of different networks
D. A network can be activity-account-assigned and header-account-assigned