Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
A. Network profile
B. Project profile
C. Parameters for the network type
D. Network type
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
A. The field key is the default value for the WBS element and the activities too.
B. The tab user fields is invisible.
C. The field key is hard coded in the WBS element.
D. The field key is the default value only for the WBS element.
Which objects can be used to specify settlement rules? Note: There are 2 correct answers to this question?
A. Standard WBS elements
B. Network header for activity-account-assigned networks
C. WBS elements
D. Network activity for activity-account-assigned networks
Where do you maintain the length of the project ID?
A. Special characters
B. Project coding mask
C. Project profile
D. Project type
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note: there are 3 correct answer for this question.
A. You can create several WBS elements per level.
B. A new work breakdown structure must contain up to 10 levels.
C. A WBS element of the new project can be assigned to a different project definition.
D. WBS element can be a planning element, an account assignment element, and a billing element at the same time.
E. The WBS structure can contain several level 1 WBS element,
Resources
Which of the following transactions can you use to post actual cost for external processing?
Note : there are 2 correct answer for this question.
A. Approval of a service entry sheet
B. Posting a goods receipt
C. Creating a service entry sheet
D. Approval of a good receipt.
E. Creating a purchase order.
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are 3 correct answers to this question
A. Confirm production order
B. Stock transfer posting
C. Generate purchase requisition
D. Generate delivery
E. Cancel goods issue
You want to create a reservation for a material component assigned to a network activity.
However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation?
Note: There are 2 correct answers to this question
A. The availability check for material components indicates missing parts
B. The material master is set to external procurement
C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never"
D. The material is assigned to the activity as a non-stock material
Which sets of dates can be used to schedule networks? Note: There are 2 correct answers to this question
A. Basic dates
B. Forecast dates
C. Baseline dates
D. Planned dates
Where can you assign the use status profile for WBS elements? Note: There are 3correct answers to this question
A. In the project profile
B. In the project version
C. In the project type
D. In the project definition of a standard WBS
E. In the operative WBS element