What are the Project Procurement Management processes?
A. Conduct Procurements, Control Procurements, Integrate Procurements, and Close Procurements
B. Estimate Procurements, Integrate Procurements, Control Procurements, and Validate Procurements
C. Plan Procurement Management, Conduct Procurements, Control Procurements, and Close Procurements
D. Plan Procurement Management, Perform Procurements, Control Procurements, and Validate Procurements
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
A. External
B. Internal
C. Mandatory
D. Discretionary
Which type of graphic is displayed below?

A. Work breakdown structure
B. Context diagram
C. Control chart
D. Pareto diagram
The following chart contains information about the tasks in a project.

Based on the chart, what is the schedulevariance (SV) for Task 8?
A. -2,000
B. -1,000
C. 1,000
D. 2,000
An issue log is an input to which Project Human Resource Management process?
A. Manage Project Team
B. Acquire Project Team
C. Plan Human Resource Management
D. Develop Project Team
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Project Management
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
A. Project Time Management
B. Project Cost Management
C. Project Scope Management
D. Project Human Resource Management
When addressing roles and responsibilities, which item ensures that the staff has the skills required to complete project activities?
A. Authority
B. Role
C. Competency
D. Responsibility
Which is an output from Distribute Information?
A. Earned value analysis
B. Trend analysis
C. Project records
D. Performance reviews
Which of the following are an enterprise environmental factor that can influence the Identify Risks process?
A. Work performance reports
B. Assumptions logs
C. Network diagrams
D. Academic studies