An activity is to be completed within a fixed time period and thetotalamount of work is fixed.
What duration type should be used?
A. Fixed Units
B. Fixed Duration and Units/Time
C. FixedUnits/Time
D. Fixed Duration and Units
Select the true statement regarding the ability to create projects.
A. Any Responsible Manager can create a project.
B. Any user can create a project
C. Any Project Manager can create a project.
D. Any Admin Super user can create a project.
Identify two true statements regarding the rolling up of data within a Work Breakdown Structure (WBS).
A. Actual Data rolls up to a Parent level.
B. Actual Data rolls up to a Portfolio level.
C. Actual Data rolls up to a Resource level.
D. Actual Data rolls up to Program level
E. Actual Data rolls up to a Project level.
When viewing the Resource Usage Profile using the date interval of Week/Day1, resource a being displayed only on Sundays for every resource being analyzed.
Why are all of the resource allocations being displayed on the same day of the week rather than across the dayswhen they are scheduled to occur?
A. All resources are assigned to the project's default calendar, and have been over allocated to other projects.
B. The resource calendar assigned to the resources was deleted by the System Administrator.
C. On the General tab. In the Admin Preferences dialog box, the first day of the week field is set to Sunday.
D. On the Resource Analysis tab, in the User Preferences dialog box, the "Interval for time- distributed resources calculations" fieldisset to "week."
What is the highest level of a Work Breakdown Structure (WBS)
A. Enterprise
B. Portfolio
C. Program
D. Project
Weighed Project codes .
A. are rarely used due to maintenance issues
B. are used to calculate Project Score
C. are used at the Activity level
D. are assigned by the System Administrator
You are a Portfolio Manager witha filter that has been set to identify and assignprojects to yourportfolio. You are in Primavera P6 EPPM Web Interface.
How could you be certain that the list of projects in your portfolio is complete?
A. by manually hiding projects
B. by manually adding new projects
C. by manually refreshing the filter
D. by manually updating projects
You are a Project Manager who ismanaging several projects in Primavera P6 EPPM Web interface.
Identify the valid navigation options for opening a project in the Web interface.
A. In the Personal Workspace/GANTT Chart portlet, double-click the project name.
B. In the Personal Workspace/My Projects, click the project name.
C. In Portfolios/Executive Summary click the project name.
D. In Portfolios/GANTT Chart click the project name.
By default, a Role's limit is determined by .
A. the manually entered value on the Limit tab in the Role Dictionary
B. the combined limit of all resources assigned to the Role
C. the combined limit of all primary resources assigned to the Role
D. the combined limit of all primary resources assigned to the Role with a proficiency of Skilled higher
Identify three best practice uses of Notebook topics.
A. Document processes.
B. Explain a Constraint.
C. Send out an email alert.
D. Explain baseline update.
E. Change User Access.
F. Update Actual Costs.
G. Provide additional status information